Transpennine Route Upgrade - East of Leeds
We are helping to deliver essential upgrades between Leeds and York, as part of Network Rail’s Transpennine Route Upgrade (TRU).
We are delivering essential upgrades between Leeds and York, as part of Network Rail’s Transpennine Route Upgrade (TRU).
TRU is a multi-billion pound, transformative, long-term railway infrastructure programme that will improve connectivity in the North. It will support economic growth in the North and deliver real benefits for passengers and communities along this pivotal rail artery.
Stretching across the North of England between York and Manchester, via Leeds and Huddersfield, the 76-mile Transpennine railway serves 23 stations, crosses over and dips under 285 bridges and viaducts, passes through six miles of tunnels, and crosses over 29 level crossings.
The East of Leeds part of TRU is between York and Church Fenton. This contract was awarded in October 2017 to the TRU East Alliance of Network Rail, VolkerRail, J. Murphy and Sons and Siemens.
Electrification
In August 2022, the alliance installed the first section of new electric overhead wires on a mainline in Yorkshire for over 25 years, marking a step-change in progress for the multi-billion-pound Transpennine Route Upgrade.
The OLE was installed between Church Fenton and Colton Junction – where trains from Leeds join the East Coast Main Line towards York. At the end of 2022, the alliance had installed over 37km of new overhead line and over 270 new steel masts, which carry the overhead electric wires.
Energisation is planned for Spring 2025 which will allow more environmentally friendly hybrid trains to run at speeds of up to 125mph; 30mph faster than the line’s current speed.
In January 2025, the OLE between Church Fenton and Cross Gates will be constructed, with energisation planned at Easter 2027. The final section around Neville Hill will be commissioned in late 2028.
Track renewals
In December 2022 the alliance successfully installed a brand new track connection in and out of Holbeck depot in Leeds, so that Northern’s train fleet could enter and exit the depot much more efficiently. The work assists reliability and creates additional capacity on the line, allowing more trains to run, as the line can be used as a key diversionary route to keep passengers moving by train during major upgrades on the main line between York and Leeds, and Leeds and Huddersfield.
In February 2024, the alliance started the final section of track renewals between Colton Junction and York. This five mile stretch of track is one of the busiest sections of railway in the North, and a major junction where trains from Leeds meet the East Coast Main Line towards York and where over 250 freight or passenger trains pass through each day, around one very five minutes.
Once completed, the alliance will have replaced rail, sleepers and ballast on over 23km of track, extending its life and enabling trains to run faster with the line speed increasing to 125mph.
To support the construction of the main core route works, diversionary and depot stabling enhancements were commissioned; Castleford was commissioned in October 2022, and Holbeck December 2022. Shipley is planned for 2026.
Track renewals and drainage works between Church Fenton and Neville Hill are due to commence in January 2025.
Power upgrades
In August 2023, the Alliance commissioned two brand new Principal Supply Points at Colton Junction and Church Fenton Junction, along with 14km of feeder renewals and 23 new FSPs, to replace the existing life expired signalling power supplies. This included the fit out of the new Church Fenton PSP building complex along with extensive refurbishment and upgrades at Colton Junction.
In February 2024, the Alliance began installing junction lighting at strategic junctions between Church Fenton and York, and in December 2024, the official opening of Castleford station’s new fully accessible second platform took place.
The improvements to the station, tracks and signalling system has increased capacity, which will boost the reliability of existing services and allows more trains to run through Castleford.
The opening of the second platform, also marked the completion of the first major station improvement scheme to be delivered by the Transpennine Route Upgrade, and represented a major investment at the station.
Sustainability
To help reduce our carbon footprint, the alliance, with the help of Network Rail, has recycled old sleepers and rail to renew the tracks in a local train depot, providing additional capacity for the TOC during the disruptive works on the route.
When complete, across the full 76-mile route, rail passengers will be helping to save up to 87,000 tonnes of carbon emissions each year – equivalent to 5.9 million car journeys along the same route. For people living near the railway, it will also mean better air quality and quieter trains.
We are focussed on developing the potential infrastructure enhancements that will lead to faster, more frequent and more reliable train services across the north
Paul McKeown Director of Route Sponsorship for Network Rail’s London North Eastern and East Midlands route